Hi Kanha. I can tell you how long does it take to renovate a small bathroom. Recently, I got my small bathroom updated to give it a modern look. It took around three weeks for my small bathroom renovation. Moreover, it completely depends on what you want to get done in your bathroom.
How Long Does It Take to Remodel a Small Bathroom?
A small bathroom renovation's completion time might vary based on several aspects, including fixture installation, tiling, plumbing, electrical and finishing touches. For my small bathroom, it took the following time:
Demolition - 2 days
Rough Carpentry - 1 day
Plumbing Changes - 2 days
Electrical Work - 1 day
Initial Inspection - 1 day
Insulation - 3 days
Complete Drywall - 2 days
Painting - 1 day
Tiling Work - 2 days
Flooring - 2 days
Cabinetry and Trim - 1 day
Hookups and Fixtures - 2 days
Final Inspection: 1 day
Furthermore, the number of days for your bathroom renovation can increase based on the project's scope and the difficulty of the work required. I hope this helps you get an idea of how long should it take to remodel a small bathroom.
Get Your Small Bathroom Renovated in Less Time with NoBroker Renovation. Read more -How much does it cost to renovate a bathroom?
Your Feedback Matters! How was this Answer?
Shifting, House?
✔
Lowest Price Quote✔
Safe Relocation✔
Professional Labour✔
Timely Pickup & DeliveryIntercity Shifting-Upto 25% Off
Check Prices
Intracity Shifting-Upto 25% Off
Check Prices
City Tempo-Upto 50% Off
Book Now
Last year, I intended to remodel my bathroom. There were family gatherings at my house, so I wanted to finish it as quickly as I could. So, before beginning the makeover, I did some online research to find out how long does it take to do a bathroom renovation.
I discovered that the project duration can vary depending on factors, like its size, complexity, and so on. A typical bathroom makeover can take five to seven weeks to complete. Let's look at the typical timeframe for bathroom renovations below.
How Long Does It Take to Remodel a Master Bathroom?
A typical remodelling schedule for a master bathroom might resemble this:
Demolition |
1 to 2 days |
Framing the layout |
2 to 4 days |
Plumbing and electricals work |
3 to 10 days |
Renovating windows and doors |
2 to 3 days |
Drywall installation |
2 to 5 days |
Tiles application |
3 to 7 days |
Painting |
2 to 5 days |
Building bathroom vanity and counters |
3 to 5 days |
Add fixtures such as sink, bathtub, and so on |
2 to 4 days |
Miscellaneous work |
2 to 4 days |
This timeline can extend if there are additional complexities or customisation involved. If you can’t do it on your own, then it is advisable to contact professionals and make a thorough strategy. I hope you got an idea of how long does it take to renovate bathroom.
Get renovation services at a low cost via NoBroker. Design your washroom or bathroom from the expert designers here. Read more -How much does it cost to renovate a bathroom?
How much does a full house renovation cost?
What are the standard height of bathroom fittings?
Your Feedback Matters! How was this Answer?
Shifting, House?
✔
Lowest Price Quote✔
Safe Relocation✔
Professional Labour✔
Timely Pickup & DeliveryIntercity Shifting-Upto 25% Off
Check Prices
Intracity Shifting-Upto 25% Off
Check Prices
City Tempo-Upto 50% Off
Book Now
Related Questions
Related Questions in Bathroom Renovation
Most Viewed Questions
Recently Published Questions
Authors Of The Question
Recently Answered Questions
0 Total Answers
How Long Does It Take to Do a Bathroom Renovation?
Kanha
178 Views
2 Answers
1 Year
2023-08-29T19:49:57+00:00 2023-08-30T15:29:11+00:00Comment
Share