Constructing a house is a huge deal and you need to take care of every aspect. How much material is required, how much labour you’ll need, how many days will it take to complete the structure and what not. Similarly, I understand that you might have questions regarding how to calculate cement in concrete. In my struggle to find an answer to this question, I learned that it depends on various factors. My contractor helped me realise those and based on it I could understand the calculations easily. I will share with you my experience and I hope it helps you out.
Factors affecting calculation of concrete and cement in concreteWhat is the durability of concrete
What is the compressive structure and strength of concrete
What is the on-site quality control of concrete
What are the site conditions
What are the shipping charges and labour rates
These are the top factors that come to my mind when struggling to figure out how to calculate cement in concrete.
How to calculate concrete?Let us first understand this before jumping on to cement in concrete. To calculate concrete you need to know the following things:
Thickness of concrete you need
Length and width you need to cover
So considering the concrete will have a mix of cement, crushed stones, and sand in a ratio of 1:2:4. Now assuming bulk density of cement is 1440 Kg/m
3
, sand = 1450 Kg/m
3
, coarse aggregates as 1500 Kg/m
3
and dry volume of materials in 1 cum of concrete is 1.54.
So, how to calculate cement in concrete? This is how:
Quantity of Cement in 1 CUM Concrete will be = 1.54x 1/7 x 1440 =
316.8kgs using the formula: Quantity of Materials in kgs = Dry Volume of Materials X (Portion of materials in Ratio / Sum of Ratios ) X Density of Materials
Using this formula, the sand requirement for the same quantity will be 638 kgs while the quantity of aggregates will be 1320 kgs.
I hope this helps you out.
Redecorating your home and need the best advice? Hop on a free consultation call with NoBroker Home Interior experts Read more: How much cost to paint a house? How much cement and sand need for plastering? How much does concrete cost per sq ft?Your Feedback Matters! How was this Answer?
Shifting, House?
✔
Lowest Price Quote✔
Safe Relocation✔
Professional Labour✔
Timely Pickup & DeliveryIntercity Shifting-Upto 25% Off
Check Prices
Intracity Shifting-Upto 25% Off
Check Prices
City Tempo-Upto 50% Off
Book Now
Related Questions
Related Questions in Build Extra Space
Most Viewed Questions
Recently Published Questions
Authors Of The Question
Recently Answered Questions
0 Total Answers
How to calculate cement in concrete?
Rati
2133 Views
2 Answers
2 Year
2022-03-07T14:01:18+00:00 2023-08-08T14:40:22+00:00Comment
Share