Experience The NoBrokerHood Difference!

Set up a demo for the entire community

Thank You For Submitting The Form
Home / Legal / Documentation / What is difference between fit out and OC. How many months after fitout you get OC?
Q.

What is difference between fit out and OC. How many months after fitout you get OC?

view 10929Views

4 Year

Comment

5 Answers

7 2020-11-05T18:24:58+00:00
Best Answer
There is a huge difference between fit out possession and getting a possession after receiving an OC. Fit out possession is basically a possession given to the owner which still has legal or some civil work left. You need to pay the entire amount to the builder while acquiring the fit out possession. On the other hand, OC is a certificate that establishes that the housing apartment in place has the required civic infrastructure, including sanitation, water, electricity and such other basic amenities. Many builders offer fit out possession but, it is generally risky to accept this possession as the legal formalities are still pending. Speaking about the possession time period after fit out possession, there is no definite time period when you might get an OC. At times, you might not even receive an OC if the construction and facilities don’t meet the authority rules and regulation. However, you can always deny to accept the fit out possession until you get the OC and the builder cannot charge you any kind of penalty for this.
Fit-out and Occupation Certificate (OC) are terms commonly used in the context of real estate, especially in commercial and residential property development. Here’s a breakdown of the differences:

Fit-Out:

  • Definition: Fit-out refers to the process of making an interior space suitable for occupation. This can include everything from installing flooring, lighting, and partitions to adding furniture and fixtures. Fit-outs are often categorized into:
    • Shell and Core: The basic structure is completed, and the internal space is left unfinished for the occupant to complete.
    • Category A Fit-Out: Basic fittings such as ceilings, lighting, and HVAC systems are installed.
    • Category B Fit-Out: Tailored finishes and fixtures are added according to the tenant’s specific requirements.
  • Purpose: The main purpose of a fit-out is to customize a space to meet the specific needs of the tenant or owner.

Occupation Certificate (OC):

  • Definition: An Occupation Certificate (OC) is a legal document issued by the local authorities or a certifier after the completion of construction. It certifies that the building or a part of it is fit for occupancy and complies with all relevant building codes, regulations, and safety standards.
  • Purpose: The OC is required to legally occupy a building. Without it, occupying the premises may be considered illegal.

Timeline Between Fit-Out and OC:

  • The timeline for receiving an Occupation Certificate after the fit-out can vary widely based on several factors:
    • Regulatory Requirements: The speed of the inspection and approval process by local authorities.
    • Scope of Fit-Out Work: If the fit-out work is extensive or requires significant structural changes, the timeline might be longer.
    • Compliance: Ensuring that all the fit-out work complies with building codes and safety regulations is crucial for obtaining the OC.
In many cases, the OC is applied for after the completion of the fit-out. The timeline can range from a few weeks to a few months, depending on the complexity of the project and the efficiency of the local regulatory body. In general, the fit-out must be completed first, and all necessary inspections must be passed before the OC can be issued. In some places, partial OCs can be granted if only part of the building is ready for occupation while the rest is still under construction.
0 2023-09-30T22:34:38+00:00

I think from a customer's point of view, it is important to understand what is soft possession and the difference between fit-out and OC, and to be aware of the timeline involved in obtaining an OC. This information can help you to make informed decisions about the purchase or occupancy of a building.

Fit Out and Soft Possession Meaning

Fit-out and OC are two different terms related to the construction and occupancy of a building.

Fit out charges meaning refer to the process of finishing the interior of a building to make it ready for use. This may include installing partitions, ceilings, flooring, and other finishes, as well as installing fixtures and fittings such as lighting, plumbing, and electrical wiring.

OC stands for Occupation Certificate. It is a certificate issued by the local authority certifying that the building is safe and habitable and that it meets all applicable building codes and regulations.

Difference between fit-out and OC:

Fit-out is the process of finishing the interior of a building, while OC is a certificate issued by the local authority certifying that the building is safe and habitable.

Fit-out is typically done by the developer or the building owner, while the OC is applied for and issued by the local authority.

Fit-out can begin once the construction of the building is complete, while the OC cannot be issued until the building has passed all necessary inspections.

How many months after fit-out do you get OC?

The time it takes to obtain an OC after fit-out varies depending on a number of factors, such as the size and complexity of the building, the workload of the local authority, and any unforeseen delays. However, it is generally expected that the OC will be issued within a few months of completing the fit-out.

I hope now you understand what is soft possession and fit out possession.

Navigate legal matters with confidence using NoBroker’s support. Read More: What is Difference Between Ownership and Possession? How to Get Ownership Certificate: A Guide?

Up until a few months back, I had only heard about commercial property fit-outs. I had no idea about residential fit out period meaning. So, I asked a few of my friends and this is what they told me. 

Opt for NoBroker’s legal services to get your property documents verified.

What is fit out possession?

Builders in the Noida area provide "Fit-out" letters to their clients, indicating that they have requested a Completion/Occupation Certificate from the Noida Authority. Additionally, flat allottees are permitted to temporarily occupy their units for the objective of interior design and fit-out during this time. The lease documents must be finalised before buyers can move into their homes, according to the developers.

What is difference between fit out and OC?

Fit out possession or soft possession is given to home buyers by developers typically once the construction is completed and while the OC application is in progress, primarily so that the home buyer can start their interior work and move in once quickly the OC is received. Fit-out possession does not entitle a home buyer to start living in the apartment. An occupancy certificate is mandatory before residents can move in. Occupancy certificate provides a legal recognition for occupying a property. With OC in place, you get access to basic facilities like electricity, water, sanitation and other essential facilities.

If the project fulfils the eligibility criteria and there's no issue with the documents submitted, then an OC can be issued within 30 days from the date of application.

Fit out possession letter format

Date: ______________

To,

<Customer Name>

<Customer Address>

<Contact no>

SUB: Possession for Unit No ________________ situated at _______, located at ______.

Dear Mr/Ms ______________________________,

Greetings from ___ Builders.

We are delighted to hand over the keys to your ABC Homes unit number __________, which you purchased in accordance with the agreement dated __________ and registered under Registration number __________ dated.

We are pleased to note that you have acknowledged peaceful and vacant possession of the property bearing the unit number in accordance with the provisions of the apartment/villa buyer's agreement. After conducting a full and comprehensive examination of the unit and other amenities/facilities offered and after being content that the construction is in pursuance of the and conditions of the builder-buyer agreement, the standard of the materials used, amenities, fixtures, and other features, we are pleased to inform you that you have accepted peaceful and vacant possession of the property

You hereby agree and affirm that you have no claims, conflicts, disagreements, or demands against the company as of the acceptance of ownership. Additionally, you agree to sign any paperwork that may be required for your unit and the creation of the organisation of owners.

The fees for your unit's common area maintenance will start to accrue on . Throughout the handover phase, a member of our estate management staff will be on site to help you during the possession of your house. Additionally, you are entitled to use the available parking space.

Regards,

__________

Now you know fit out period meaning clearly.

Read More: What is the difference between fit-out possession and offer of possession?  What is a Certificate of Occupancy of Building? 
0 2022-07-18T18:55:04+00:00

Hey buddy,

I learned about the difference between the fit-out possession and OC certificate when I was looking to buy a property last year. I will explain it in this answer. I will also tell you about the fit-out period here.

A fit-out possession is given by developers to property buyers generally after the completion of construction and while the OC (Occupancy Certificate) application is in progress, mainly so that the property buyer can begin their interior work and move in once the Occupancy Certificate is received.

For those balancing rents and EMIs simultaneously, any arrangement to save up some money would look good. If the developer told you that he’d give you a fit-out letter and you could take possession of the property because it might take some time before the Occupancy Certificate is granted. This fit-out possession letter may tempt you into accepting the offer, but let me tell you that it’s not legal. Developer bodies like CREDAI have also mentioned that it’s not safe to accept a fit-out without an Occupancy Certificate.

An Occupancy Certificate is a legal document that’s issued after the completion of the construction, by a local planning authority or government agency. This certificate indicates that the property is in a good condition for occupancy. It is the responsibility of the developer to obtain an OC and this certificate is granted only once the building has been completed in every respect and is ready to be occupied. If the project fulfils the eligibility criteria and there’s no issue with the documents submitted, then an OC can be issued within 30 days from the date of application.

Take the Help of NoBroker’s Legal Experts and Check Whether the Property has All the Required Documents (like an Occupancy Certificate) in Place!

I know you about the OC as well as the fit out possession meaning.

What is Fit Out Period in Leave and License Agreement

I want you to know that a rent-free fit-out period is a short period that a landlord gives to his tenants before the Leave and License Agreement’s beginning.

It is mostly given in commercial properties but can be given in residential properties on rare occasions. This period is given only for renovations so that you can make the space suitable for you based on your business operations and style.

Check Out NoBroker’s Rent Agreement Services if You are Looking to Make a Legally Verified Rent Agreement!

Read more:

What is a Certificate of Occupancy of Building

How to Get a Certificate of Occupancy

How to Check Occupancy Certificate Online

This is all about the difference between fit out period and OC.

Most Viewed Questions

Recently Published Questions

Flat 25% off on Home Painting
Top Quality Paints | Best Prices | Experienced Partners