Home / Buy and Sell / Project Reviews / What is the construction status of Wadhwa Wise City project?
Q.

What is the construction status of Wadhwa Wise City project?

view 1572Views

3 Year

Comment

1 Answers

Send
1 2021-06-30T19:40:24+00:00
Best Answer
Wadhwa Wise City Panvel Construction Update as of July 2021.
  • D1: Terrace Slab completed
  • D2: Terrace Slab completed
  • D3: 19th slab in progress
  • D4: 1st slab in progress
For A-series Towers
  • A1: Terrace Slab completed
  • A2: plinth work in progress
  • A3: 1st slab in progress
  • A4: 11th slab in progress
Wadhwa Wise City Panvel launched in May 2018 and Wadhwa Wise City  possession will start from December 2022 in some towers and for the rest of the blocks of Wadhwa Wise City Panvel possession will start from December 2023. Currently the Wadhwa wise city construction status is that few towers outer building structure is constructed and will take a while in moving to the indoor development. Also there are many other towers on which the ground level work is done. Wadhwa Developers are famous for serving premium products. The other floor plan and interior graphs are ready and will start with the construction once other wooden, electricity, water supply work is completed.